Minister Dave Umahi’s Ultimatum to Julius Berger: No Room for Further Variations

Minister Dave Umahi's Ultimatum to Julius Berger: No Room for Further Variations

Minister of Works, Dave Umahi, has issued a stern ultimatum to Julius Berger Nigeria regarding the completion of the Bodo-Bonny road project. The project, currently at 82% completion, has faced delays and requested variations from the contractor. Umahi clarified that the initial agreement, signed for the N199.923 billion project, stipulated a completion deadline of December 2023 with no allowance for further variations. However, Julius Berger has requested an additional N28 billion, citing various conditions for project completion.

Dave Umahi asserted the federal government’s position, offering N20 billion out of the requested N28 billion but deeming the requested variations unacceptable. He emphasized that the government cannot tolerate contractors dictating terms once a contract has been agreed upon. The Minister’s firm stance was made clear during a meeting in Abuja with Lars Ritcher, the Managing Director of Julius Berger, and the Bodo-Bonny Road Peace Committee. The Minister stressed the necessity for both parties to adhere to the agreed-upon terms and warned of enforcement actions if the contractor fails to accept the government’s offer and resume work promptly.

The Significance of the Bodo-Bonny Road Project for Rivers State

The Bodo-Bonny road project holds immense significance for Rivers State as it serves as the first road link between Bonny Island and the rest of the state. With a length of 39 kilometers, the completion of this road promises to enhance connectivity and facilitate economic growth in the region. Bonny Island, known for its oil and gas industry, has long awaited a reliable road connection to facilitate transportation of goods and services.

The delays and variations in the project have been a source of frustration for residents and stakeholders, who have eagerly anticipated the road’s completion. Minister Dave Umahi’s ultimatum to Julius Berger underscores the government’s commitment to expediting the project and ensuring its timely completion. The road is not merely a construction endeavor but a catalyst for development, promising improved access to healthcare, education, and other essential services for communities along its route.

Minister Dave Umahi’s firm stance on the Bodo-Bonny road project carries significant legal and contractual implications. By emphasizing the importance of adhering to the terms of the initial agreement, the Minister reaffirms the government’s commitment to upholding contractual obligations and ensuring accountability in public projects. His assertion that no contractor has the authority to dictate terms once a contract is in place underscores the principle of contractual sanctity and the need for mutual respect between parties.

Furthermore, Dave Umahi’s ultimatum serves as a reminder of the consequences of delays and variations in government projects. With taxpayers’ funds at stake, the Minister’s insistence on prudent financial management and adherence to project timelines reflects a broader commitment to good governance and transparency. As the deadline approaches, stakeholders will closely monitor developments, hopeful for a swift resolution that prioritizes the public interest and the timely completion of the vital infrastructure project.

Minister Dave Umahi Warns Julius Berger Over Project Demands

In a stern address to the Berger delegation, Minister Dave Umahi laid out clear terms for the continuation of the project, stating that they must either accept the government’s response to their demands or voluntarily terminate the project. Umahi emphasized the urgency of the matter, underlining the government’s commitment to completing the project within the stipulated timeframe. The Minister’s firm stance reflects the government’s determination to uphold its principles while ensuring the timely execution of critical infrastructure projects.

Dave Umahi’s ultimatum comes after protracted negotiations over project variations, with Berger initially requesting N28 billion, while the Ministry was only willing to allocate N13.8 billion. Despite agreeing to pay N20 billion, a N15 billion disparity remained, highlighting the contentious nature of the discussions. The Minister’s insistence on adherence to government directives underscores the need for accountability and transparency in contractual agreements, particularly in the realm of public infrastructure development.

Assurance of Project Continuity and Quality

Addressing concerns regarding the potential abandonment of the project by Julius Berger, Minister Dave Umahi reassured the Boddo-Bonny Road Peace Committee that regardless of Berger’s decision, the project would proceed without delay. He affirmed the government’s commitment to delivering the project by the end of the year, underscoring the importance of continuity and quality in infrastructure development.Dave Umahi’s assurance reflects the government’s unwavering resolve to prioritize the interests of the public and uphold its responsibilities to taxpayers.

Dave Umahi’s remarks also serve as a reminder to Julius Berger of its obligations to demonstrate humility and solidarity in its dealings with the government, particularly during economic challenges. The Minister’s insistence on mutual respect and cooperation underscores the need for a collaborative approach to project management, wherein both parties work towards achieving shared objectives. By emphasizing the non-negotiable nature of government directives, Umahi reinforces the principle of accountability and underscores the importance of upholding national interests above all else.

Implications of Dave Umahi’s Ultimatum and Executive Order

Minister Dave Umahi’s unequivocal stance against Berger’s demands signals a shift in the dynamics of public-private partnerships in infrastructure development. His assertion that “nobody dictates to me” underscores the government’s authority in setting the terms of engagement with contractors, reaffirming its sovereignty in decision-making processes. By invoking the Executive Order and tax credit provisions,Dave Umahi reinforces the legality and legitimacy of the government’s position, highlighting its adherence to established protocols and regulations.

Furthermore,Dave Umahi’s ultimatum to Berger carries broader implications for future contractual agreements and project negotiations. It serves as a cautionary tale for contractors, emphasizing the importance of compliance with government directives and the consequences of overstepping boundaries. Additionally, it underscores the government’s commitment to fiscal responsibility and prudent resource allocation, ensuring that taxpayer funds are utilized efficiently and effectively. Overall, Minister Dave Umahi’s firm stance reflects a commitment to transparency, accountability, and the effective delivery of public infrastructure projects for the benefit of all citizens.


Discover more from OGM News NG

Subscribe to get the latest posts sent to your email.

Leave a Reply

Your email address will not be published. Required fields are marked *

Discover more from OGM News NG

Subscribe now to keep reading and get access to the full archive.

Continue reading